Steel Structures

Pipe Rack Design Guide (Part 2): Connection Detail & Checklist

Structural Notes · No. 08 · 11 Aug 2026 · 12 min read

8. Beam-to-column connections

8.1. Connection philosophy for pipe racks

  • Bolted connections preferred — minimise field welding for speed and quality.
  • Transverse direction: moment connections (rigid frames).
  • Longitudinal direction: shear connections (beams act as struts or are braced).
  • All connections must transfer: shear + moment (if rigid) + axial (if strut).

8.2. End-plate moment connection (most common)

Figure 4. Bolted end-plate moment connection.
Figure 4. Bolted end-plate moment connection.
  • Type: flush or extended end-plate.
  • Reference: AISC Design Guide 4 / 39.

Design steps:

  • 1. Determine required moment (Mu) and shear (Vu) at the connection.
  • 2. Select bolt configuration (4-bolt, 8-bolt).
  • 3. Calculate end-plate thickness (yield-line method).
  • 4. Check bolt tension (including prying action).
  • 5. Check column flange bending / web yielding / web crippling.
  • 6. Add stiffeners if the column is inadequate.

Key design checks

CheckWhat to verify
Bolt tensionTb ≥ Tu (including prying)
End-plate bendingtp ≥ required (yield-line)
Column flange bendingtf ≥ required, or add stiffeners
Column web yieldingRn ≥ beam flange force
Column web cripplingRn ≥ beam flange force
Column web panel zone shearRv ≥ required
Shear at bolt groupRn ≥ Vu

8.3. Shear connection (simple connection)

  • Used for: non-moment beams, struts, secondary framing.
  • Types: single/double angle, shear tab (single plate), end-plate shear.
  • Reference: AISC Manual Part 10.
  • Design checks: bolt shear, bearing, net section, block shear.

9. Base plate & anchor bolt design

9.1. Base plate design per AISC Design Guide 1

Figure 5. Base plate: pinned vs fixed configurations.
Figure 5. Base plate: pinned vs fixed configurations.
TypeMoment transferWhen to use
Pinned baseNo moment (shear + axial only)Top of column has a moment connection to the beam
Fixed baseTransfers moment to the foundationCantilever columns, tall racks, large lateral loads

9.2. Fixed base design steps

  • 1. Determine loads: Pu (axial), Mu (moment), Vu (shear).
  • 2. Base plate size (B × N): must fit within the column footprint + clearance; check concrete bearing fp ≤ φ(0.85f′c)√(A₂/A₁).
  • 3. Base plate thickness (tp): based on bending of the plate cantilever (m, n dimensions); simplified tp = 2.11 × √(Mu,plate / (Fy × B)).
  • 4. Anchor bolts: tension Tu = Mu/d − Pu/nbolts (for small axial); shear transferred by friction, bearing or shear lugs.
  • 5. Anchor bolt embedment: per ACI 318 Chapter 17 (anchorage to concrete).

9.3. Anchor bolt checks (ACI 318 Ch.17)

Failure modeWhat to check
Steel tensionBolt tensile capacity
Concrete breakout (tension)Cone pullout, edge effects
Concrete pulloutBearing on bolt head/nut
Steel shearBolt shear capacity
Concrete breakout (shear)Edge distance, pier size
Concrete pryoutShort bolts

10. Bracing design

10.1. Vertical bracing (longitudinal)

  • Purpose: resist longitudinal lateral loads (friction, wind, seismic).
  • Types: X-bracing (most common), inverted V (chevron), single diagonal.
  • Location: every 3–5 bays. Coordinate with piping expansion loops.

10.2. Design checks for bracing members

Tension member:      Pn = Fy × Ag   (yielding)
                     Pn = Fu × Ae   (rupture)

Compression member:  Pn = Fcr × Ag  (buckling — AISC Ch. E)

Slenderness:         KL/r ≤ 200  (compression)
                     L/r  ≤ 300  (tension — recommended)

10.3. Horizontal struts

  • Connect bents at beam level in the longitudinal direction.
  • Must resist: friction force, tributary wind, strut force from the bracing.
  • Often designed as compression members (they can buckle when the friction load reverses).
  • Effective length: typically KL = the full bay length between bents.

10.4. Bracing connection (gusset plate)

  • Gusset plates must transfer the brace force to the beam-column joint.
  • Whitmore section for tension/compression capacity.
  • Thornton method for gusset plate buckling.
  • Block shear check at the bolt group.
  • Clearance: ensure the 2t linear clearance (AISC requirement).

11. Practical detailing — tips from experience

11.1. Member orientation

  • Columns: strong axis (x-x) oriented in the transverse direction — moment frame action is transverse, so maximum bending is about the strong axis.
  • Beams: strong axis resists gravity loads (obvious).
  • Struts: weak-axis buckling must be checked — it often controls.

11.2. Future expansion

  • Design for 10–25% additional pipe load capacity.
  • Leave space for future pipe levels.
  • Foundation design should account for potential future uplift.
  • Bracing locations should allow future piping runs.

11.3. Access & maintenance

  • Clear height under the lowest beam ≥ 4.5 m (15 ft) for vehicle access.
  • Maintenance platforms at each beam level (if required by operations).
  • Ladder and stairway access per OSHA/local codes.
  • Avoid placing bracing where it blocks access routes.

11.4. Fireproofing

  • Required in some jurisdictions or by project specification.
  • Typically intumescent paint or cementitious spray.
  • Adds dead load (15–30 kg/m² of member surface area).
  • Affects connection details — clearances are needed for fireproofing application.

12. Pipe support interaction

12.1. Support types

TypeMovement allowedForce transfer
RestFree in all horizontal directionsVertical only (+ friction)
GuideAxial onlyVertical + lateral (no axial restraint)
AnchorNone (fixed)Vertical + lateral + axial (full restraint)
SpringVertical movementVariable vertical support

12.2. Information required from the piping team

  • Pipe sizes, insulation thickness, content density.
  • Support locations and types (rest / guide / anchor).
  • Anchor loads (Fx, Fy, Fz) from piping stress analysis.
  • Thermal expansion ranges and movement directions.
  • Hydrotest requirements (which pipes, in what sequence).
  • Future piping additions.

13. Deflection limits

ConditionLimitReference
Beam vertical deflection (DL+LL)L/240AISC / project spec
Beam vertical deflection (LL only)L/360AISC / project spec
Lateral drift (transverse)H/100 to H/200Project spec / PIP
Lateral drift (longitudinal)H/200Project spec
Column vertical shorteningPer piping toleranceCoordinate with piping

14. Design checklist — complete project workflow

Phase 1: Input data collection

  • Plot plan and pipe rack routing layout.
  • Pipe list with sizes, insulation, content, temperatures.
  • Cable tray layouts and weights.
  • Geotechnical report (bearing capacity, seismic parameters).
  • Project design criteria document.
  • Piping stress analysis data (anchor/guide loads).

Phase 2: Configuration design

  • Bent spacing determined (matching pipe support spacing).
  • Rack width determined (from the pipe routing study).
  • Number of beam levels determined.
  • Column height determined (clearance requirements).
  • Bracing bay locations selected (coordinated with piping).
  • Future expansion allowance incorporated.

Phase 3: Structural analysis

  • Load calculation complete (D, Do, Dt, L, Ff, W, E).
  • Load combinations per AISC/ASCE 7 established.
  • Transverse bent analysis complete.
  • Longitudinal braced bay analysis complete.
  • Second-order effects (P-Δ) included.
  • Member design ratios ≤ 1.0 (target 0.7–0.9).

Phase 4: Connection design

  • Beam-to-column moment connections designed.
  • Base plate and anchor bolts designed.
  • Bracing gusset connections designed.
  • Strut connections designed (shear + axial).
  • Pipe support attachments detailed.

Phase 5: Foundation design

  • Foundation reactions extracted from the structural analysis.
  • Pedestal/pier sizing (gravity + moment + shear).
  • Anchor bolt embedment per ACI 318 Ch.17.
  • Foundation stability (overturning, sliding).
  • Hydrotest load case checked on the foundation.

Phase 6: Drawing & documentation

  • General arrangement drawings.
  • Member schedule with sizes and materials.
  • Connection details (standard and special).
  • Foundation plan and details.
  • Bill of materials.
  • Calculation report.

15. Related standards — quick reference

StandardScopeKey content
AISC 360Steel designMember design, stability, connections
AISC 341Seismic steel designSpecial provisions for seismic zones
AISC Design Guide 1Base plates & anchor rodsPlate thickness, anchor design
AISC Design Guide 4/39End-plate connectionsMoment connection design
ASCE 7Loads and load combinationsWind, seismic, load factors
ASCE PetrochemicalIndustrial structure guidelinesNon-building structure provisions
ACI 318Concrete designFoundation, anchor bolt embedment
PIP STC01015Pipe rack design criteriaIndustry practice, load definitions

Part 2 summary

#ContentKeyword
1End-plate moment connection = standard for pipe rack bentsEnd-Plate
2Base plate: pinned or fixed — always minimum 4 anchor bolts4 Bolts Min
3Vertical bracing every 3–5 bays, coordinate with pipingBracing Layout
4Gusset plate: Whitmore + Thornton + block shearGusset Checks
5Strong axis of column oriented in the transverse directionColumn Orientation
6Design for 10–25% future expansion capacityFuture Growth
7Pipe support data from the piping team = critical inputCoordination
8Complete checklist from input data to documentation6-Phase Workflow

Part of the series “Structural design for industrial facilities” — Roberto Structural. The content is technical guidance; the engineer remains responsible for checking and adapting it to the conditions of each project and the requirements of the governing code. © Compiled from AISC 360, ASCE 7, AISC Design Guides, PIP Standards and practical project experience.

Share this article
View all articles